Fort Tryon Park Path and Stair Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the path and stairs in Fort Tryon Park that lead to the Cloisters. The fencing and lighting along the pathway will also be reconstructed and upgraded.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2010
Projected Completion Date: December 2012
Completion Date: April 2013

Procurement

Start Date: April 2013
Projected Completion Date: January 2014
Completion Date: April 2014

Construction

Start Date: June 2014
Projected Completion Date: June 2015
Completion Date: April 2015

Understand how we build parks.

Funding

Total Funding: $697,000
Funding Source: City Council

Location

Fort Tryon Park, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024