Fort Tryon Park Path and Stair Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the path and stairs in Fort Tryon Park that lead to the Cloisters. The fencing and lighting along the pathway will also be reconstructed and upgraded.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2010
Projected Completion Date:
December 2012
Completion Date:
April 2013
Procurement
Start Date: April 2013
Projected Completion Date:
January 2014
Completion
Date:
April 2014
Construction
Start Date: June 2014
Projected Completion Date:
June 2015
Completion Date: April 2015
Understand how we build parks.
Funding
Funding Source: City Council
Location
Fort Tryon Park, Manhattan
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks