Highbridge Park Brush Stairway Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will demolish and reconstruct the Brush Stairway in Highbridge Park

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2009
Projected Completion Date: January 2010
Completion Date: November 2010

Procurement

Start Date: November 2010
Projected Completion Date: August 2011
Completion Date: July 2011

Construction

Start Date: September 2011
Projected Completion Date: September 2012
Completion Date: February 2014

Understand how we build parks.

Funding

Total Funding: $792,000
Funding Sources:
  • Borough President
  • Private

Location

Highbridge Park, Manhattan
Near West 158th Street between Edgecombe Avenue and Harlem River Drive
Community Board: 10, 12

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024