Fort Tryon Park Fieldhouse Staircase Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the staircase and perform site work at the Fort Tryon Park fieldhouse.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2011
Projected Completion Date: January 2015
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: December 2016

Construction

Start Date: March 2017
Projected Completion Date: March 2018
Completion Date: March 2018

Understand how we build parks.

Funding

Total Funding: $1,210,000
Funding Source: Borough President

Location

Fort Tryon Park, Manhattan
Broadway between Arden Street and Dongan Place, Manhattan
Community Board: 12

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project