Sherman Creek Entrance, Path, and Fencing Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct an entrance, path and fencing at Sherman Creek.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2006
Projected Completion Date:
September 2012
Completion Date:
October 2012
Procurement
Start Date: October 2012
Projected Completion Date:
July 2013
Completion
Date:
June 2013
Construction
Start Date: September 2013
Projected Completion Date:
September 2014
Completion Date: May 2014
Understand how we build parks.
Funding
Funding Source: City Council
Location
Sherman Creek, Manhattan
Dyckman Street at 10th Avenue
Community Board: 12
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025