White Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct White Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2011
Projected Completion Date: June 2013
Completion Date: January 2014

Procurement

Start Date: January 2014
Projected Completion Date: October 2014
Completion Date: May 2015

Construction

Start Date: June 2015
Projected Completion Date: June 2016
Completion Date: June 2016

Understand how we build parks.

Funding

Total Funding: $2,964,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

White Playground, Manhattan
Lexington Avenue between East 105th Street and East 106th Street
Community Board: 11

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024