White Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct White Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2011
Projected Completion Date:
June 2013
Completion Date:
January 2014
Procurement
Start Date: January 2014
Projected Completion Date:
October 2014
Completion
Date:
May 2015
Construction
Start Date: June 2015
Projected Completion Date:
June 2016
Completion Date: June 2016
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
White Playground, Manhattan
Lexington Avenue between East 105th Street and East 106th Street
Community Board: 11
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024