Randall's Island Hell Gate Pathway Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct the Hell Gate pathway.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2012
Projected Completion Date: December 2012
Completion Date: November 2013

Procurement

Start Date: November 2013
Projected Completion Date: August 2014
Completion Date: May 2015

Construction

Start Date: July 2015
Projected Completion Date: July 2016
Completion Date: August 2016

Understand how we build parks.

Funding

Total Funding: $1,246,000
Funding Source: State

Location

Wards Island Park, Manhattan
Below the Amtrak viaduct, from Column 26 and Central Road to Wards Island Wastewater Treatment Plant.
Community Board: 11

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025