Randall's Island Hell Gate Pathway Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct the Hell Gate pathway.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2012
Projected Completion Date:
December 2012
Completion Date:
November 2013
Procurement
Start Date: November 2013
Projected Completion Date:
August 2014
Completion
Date:
May 2015
Construction
Start Date: July 2015
Projected Completion Date:
July 2016
Completion Date: August 2016
Understand how we build parks.
Funding
Funding Source: State
Location
Wards Island Park, Manhattan
Below the Amtrak viaduct, from Column 26 and Central Road to Wards Island Wastewater Treatment Plant.
Community Board: 11
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025