Randall's Island Western Shore Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct a portion of the western shore on Randall's Island.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2011
Projected Completion Date:
June 2016
Completion Date:
August 2016
Procurement
Start Date: August 2016
Projected Completion Date:
May 2017
Completion
Date:
February 2018
Construction
Start Date: March 2018
Projected Completion Date:
March 2019
Completion Date: March 2019
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- State
Location
Randall's Island Park, Manhattan
Randall's Island, Harlem River
Community Board: 11
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024