Marcus Garvey Park Public Restroom Building Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a new public restroom building and Little League building in Marcus Garvey Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2015
Projected Completion Date:
February 2016
Completion Date:
April 2016
Procurement
Start Date: April 2016
Projected Completion Date:
December 2016
Completion
Date:
June 2017
Construction
Start Date: July 2017
Projected Completion Date:
January 2019
Completion Date: July 2021
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Private
- State
Location
Marcus Garvey Park, Manhattan
18 Mount Morris Park West, between West 121st Street and West 122nd Street
Community Board: 11
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025