Frederick Johnson Park Tennis Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the tennis courts in Frederick Johnson Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2010
Completion Date: February 2012

Procurement

Start Date: February 2012
Projected Completion Date: October 2012
Completion Date: October 2012

Construction

Start Date: March 2013
Projected Completion Date: March 2014
Completion Date: October 2013

Understand how we build parks.

Funding

Total Funding: $551,000
Funding Sources:
  • Borough President
  • City Council

Location

Frederick Johnson Playground, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024