Langston Hughes Playground Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the public restroom building at Langston Hughes Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2009
Projected Completion Date: August 2012
Completion Date: June 2015

Procurement

Start Date: June 2015
Projected Completion Date: March 2016
Completion Date: August 2016

Construction

Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: May 2018

Understand how we build parks.

Funding

Total Funding: $1,006,000
Funding Source: City Council

Location

Langston Hughes Playground, Manhattan
Adam Clayton Powell Jr. Boulevard and West 130th Street
Community Board: 10

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025