Riverside Park 79th Street Boat Basin Dock A Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Dock A at the 79th Street Boat Basin in Riverside Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2010
Projected Completion Date:
March 2013
Completion Date:
March 2014
Procurement
Start Date: March 2014
Projected Completion Date:
December 2014
Completion
Date:
March 2015
Construction
Start Date: May 2015
Projected Completion Date:
May 2016
Completion Date: June 2016