Riverside Park 79th Street Boat Basin Dock A Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Dock A at the 79th Street Boat Basin in Riverside Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2010
Projected Completion Date: March 2013
Completion Date: March 2014

Procurement

Start Date: March 2014
Projected Completion Date: December 2014
Completion Date: March 2015

Construction

Start Date: May 2015
Projected Completion Date: May 2016
Completion Date: June 2016

Understand how we build parks.

Funding

Total Funding: $5,592,000
Funding Sources:
  • Federal
  • Mayoral

Location

Riverside Park, Manhattan
Hudson River at West 79th Street
Community Board: 07, 09

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024