Trygve Lie Plaza Sitting Area Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the sitting area at Trygve Lie Plaza.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2009
Projected Completion Date:
September 2013
Completion Date:
March 2014
Procurement
Start Date: March 2014
Projected Completion Date:
November 2014
Completion
Date:
January 2015
Construction
Start Date: March 2015
Projected Completion Date:
June 2016
Completion Date: June 2016
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Trygve Lie Plaza, Manhattan
First Avenue between East 41st Street and East 42nd Street
Community Board: 06