Trygve Lie Plaza Sitting Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the sitting area at Trygve Lie Plaza.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2009
Projected Completion Date: September 2013
Completion Date: March 2014

Procurement

Start Date: March 2014
Projected Completion Date: November 2014
Completion Date: January 2015

Construction

Start Date: March 2015
Projected Completion Date: June 2016
Completion Date: June 2016

Understand how we build parks.

Funding

Total Funding: $1,118,000
Funding Sources:
  • City Council
  • Mayoral

Location

Trygve Lie Plaza, Manhattan
First Avenue between East 41st Street and East 42nd Street
Community Board: 06

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/11/2024