Ramon Aponte Park Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Ramon Aponte Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2011
Projected Completion Date:
February 2013
Completion Date:
October 2014
Procurement
Start Date: October 2014
Projected Completion Date:
July 2015
Completion
Date:
July 2015
Construction
Start Date: September 2015
Projected Completion Date:
September 2016
Completion Date: June 2016
Understand how we build parks.
Funding
Funding Source: City Council
Location
Ramon Aponte Park, Manhattan
West 47th Street between 8th and 9th Avenues, Manhattan
Community Board: 04
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project