Luther Gulick Park Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Luther Gulick Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2011
Projected Completion Date:
June 2016
Completion Date:
May 2017
Procurement
Start Date: May 2017
Projected Completion Date:
February 2018
Completion
Date:
January 2019
Construction
Start Date: March 2019
Projected Completion Date:
September 2020
Completion Date: September 2020
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Federal
- Mayoral
- State
Location
Luther Gulick Park, Manhattan
Delancey Street between Willett Street and Columbia Street
Community Board: 03
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025