James Madison Plaza Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct James Madison Plaza.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2007
Projected Completion Date: August 2008
Completion Date: January 2009

Procurement

Start Date: January 2009
Projected Completion Date: October 2009
Completion Date: November 2009

Construction

Start Date: March 2010
Projected Completion Date: March 2011
Completion Date: October 2013

Understand how we build parks.

Funding

Total Funding: $2,065,000
Funding Source: Federal

Location

James Madison Plaza, Manhattan
Pearl Street, Madison Street and St. James Place
Community Board: 03

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025