Stuyvesant Square East Section Fence and Sidewalk Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the fence and sidewalks in the eastern half of Stuyvesant Square.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2010
Projected Completion Date: December 2012
Completion Date: April 2013

Procurement

Start Date: April 2013
Projected Completion Date: January 2014
Completion Date: July 2014

Construction

Start Date: October 2014
Projected Completion Date: April 2016
Completion Date: December 2016

Understand how we build parks.

Funding

Total Funding: $5,033,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Stuyvesant Square, Manhattan
Rutherford Place, Nathan D. Perlman Place, East 15th Street, East 17th Street
Community Board: 06

 