Dry Dock Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the play equipment and security lighting at Dry Dock Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2010
Projected Completion Date:
November 2012
Completion Date:
December 2013
Procurement
Start Date: December 2013
Projected Completion Date:
August 2014
Completion
Date:
November 2014
Construction
Start Date: April 2015
Projected Completion Date:
April 2016
Completion Date: December 2015
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Dry Dock Playground, Manhattan
Szold Place, Avenue D and East 10th Street
Community Board: 03
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024