Dry Dock Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the play equipment and security lighting at Dry Dock Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2010
Projected Completion Date: November 2012
Completion Date: December 2013

Procurement

Start Date: December 2013
Projected Completion Date: August 2014
Completion Date: November 2014

Construction

Start Date: April 2015
Projected Completion Date: April 2016
Completion Date: December 2015

Understand how we build parks.

Funding

Total Funding: $1,558,000
Funding Sources:
  • City Council
  • Mayoral

Location

Dry Dock Playground, Manhattan
Szold Place, Avenue D and East 10th Street
Community Board: 03

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024