Bleecker Playground and Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Bleecker Playground, including the Public Restroom Building.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2009
Projected Completion Date: September 2009
Completion Date: January 2011

Procurement

Start Date: January 2011
Projected Completion Date: October 2011
Completion Date: July 2012

Construction

Start Date: September 2012
Projected Completion Date: September 2013
Completion Date: August 2013

Understand how we build parks.

Funding

Total Funding: $473,000
Funding Source: City Council

Location

Bleecker Playground, Manhattan
Bleecker Street, Hudson Street, West 11th Street
Community Board: 02

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/11/2024