Bleecker Playground and Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Bleecker Playground, including the Public Restroom Building.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2009
Projected Completion Date:
September 2009
Completion Date:
January 2011
Procurement
Start Date: January 2011
Projected Completion Date:
October 2011
Completion
Date:
July 2012
Construction
Start Date: September 2012
Projected Completion Date:
September 2013
Completion Date: August 2013
Understand how we build parks.
Funding
Funding Source: City Council
Location
Bleecker Playground, Manhattan
Bleecker Street, Hudson Street, West 11th Street
Community Board: 02
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025