Bellevue South Park Landscape Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the landscape and complete miscellaneous site work in Bellevue South Park.

Project Timeline

Design

Assigned & Start Date: January 2010
Completion Date: October 2011

Procurement

Start Date: October 2011
Projected Completion Date: July 2012
Completion Date: August 2012

Construction

Start Date: March 2013
Projected Completion Date: November 2013
Completion Date: November 2013

Understand how we build parks.

Funding

Total Funding: $210,000
Funding Source: City Council

Location

Bellevue South Park, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project