Peck Slip Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Peck Slip.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2017
Projected Completion Date: December 2018
Completion Date: May 2019

Procurement

Start Date: May 2019
Projected Completion Date: February 2020
Completion Date: December 2019

Construction

Start Date: January 2020
Projected Completion Date: January 2021
Completion Date: January 2021

Understand how we build parks.

Funding

Total Funding: $4,787,000
Funding Sources:
  • Federal
  • Mayoral

Location

Peck Slip, Manhattan
Peck Slip between Water Street and South Street
Community Board: 01

 