Collect Pond Park Construction
-
100% complete
-
100% complete
-
100% complete
This project will expand Collect Pond Park into the adjacent parking lot and provide new plantings and a pond.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2007
Projected Completion Date:
December 2008
Completion Date:
March 2010
Procurement
Start Date: March 2010
Projected Completion Date:
November 2010
Completion
Date:
July 2011
Construction
Start Date: August 2011
Projected Completion Date:
August 2012
Completion Date: November 2013
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Collect Pond Park, Manhattan
Lafayette Street, Centre Street, Leonard Street, Franklin Street
Community Board: 01
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024