Collect Pond Park Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will expand Collect Pond Park into the adjacent parking lot and provide new plantings and a pond.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2007
Projected Completion Date: December 2008
Completion Date: March 2010

Procurement

Start Date: March 2010
Projected Completion Date: November 2010
Completion Date: July 2011

Construction

Start Date: August 2011
Projected Completion Date: August 2012
Completion Date: November 2013

Understand how we build parks.

Funding

Total Funding: $4,481,000
Funding Sources:
  • Federal
  • Mayoral

Location

Collect Pond Park, Manhattan
Lafayette Street, Centre Street, Leonard Street, Franklin Street
Community Board: 01

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024