Brooklyn Street Tree Planting FY10 (BG-810MA)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new street trees, expand sidewalk tree pits, and install tree pit guards in Brooklyn.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2010
Completion Date: August 2011

Procurement

Start Date: August 2011
Projected Completion Date: May 2012
Completion Date: April 2012

Construction

Start Date: April 2012
Projected Completion Date: October 2013
Completion Date: February 2014

Understand how we build parks.

Funding

Total Funding: $2,864,000
Funding Sources:
  • Borough President
  • Private

Location

Various locations, Brooklyn.

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024