Brooklyn Street Tree Planting FY10 (BG-810MA)
-
100% complete
-
100% complete
-
100% complete
This project will plant new street trees, expand sidewalk tree pits, and install tree pit guards in Brooklyn.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2010
Completion Date:
August 2011
Procurement
Start Date: August 2011
Projected Completion Date:
May 2012
Completion
Date:
April 2012
Construction
Start Date: April 2012
Projected Completion Date:
October 2013
Completion Date: February 2014
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Private