Bay Ridge Eco-Dock Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install a community eco-dock at American Veterans Memorial Pier.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2011
Completion Date: November 2011

Procurement

Start Date: November 2011
Projected Completion Date: August 2012
Completion Date: July 2012

Construction

Start Date: September 2012
Projected Completion Date: February 2013
Completion Date: September 2013

Understand how we build parks.

Funding

Total Funding: $933,000
Funding Sources:
  • Borough President
  • City Council

Location

American Veterans Memorial Pier, Brooklyn
Bay Ridge Avenue and Shore Road
Community Board: 10

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024