Brooklyn Street Tree Planting & Invasive Species Removal FY11
-
100% complete
-
100% complete
-
100% complete
This project will plant street trees and remove invasive species at various locations in Brooklyn.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2011
Completion Date:
October 2011
Procurement
Start Date: October 2011
Projected Completion Date:
July 2012
Completion
Date:
May 2012
Construction
Start Date: June 2012
Projected Completion Date:
September 2014
Completion Date: April 2014
Understand how we build parks.
Funding
Funding Source: Mayoral
Last updated: 01/17/2025