PS 192 Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a new playground at Brooklyn PS 192 and open the playground for the surrounding community to use outside of school hours.

Project Timeline

Design

Assigned & Start Date: July 2010
Projected Completion Date: August 2012
Completion Date: August 2012

Procurement

Start Date: August 2012
Projected Completion Date: May 2013
Completion Date: June 2013

Construction

Start Date: June 2013
Projected Completion Date: June 2014
Completion Date: June 2014

Understand how we build parks.

Funding

Total Funding: $1,394,000
Funding Sources:
  • City Council
  • Mayoral

Location

18th Avenue between 47th Street and 48th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024