Calvert Vaux Park Soccer Fields Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct two soccer fields in Calvert Vaux Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2007
Projected Completion Date: September 2007
Completion Date: December 2007

Procurement

Start Date: December 2007
Projected Completion Date: September 2008
Completion Date: June 2008

Construction

Start Date: February 2009
Projected Completion Date: February 2010
Completion Date: October 2013

Understand how we build parks.

Funding

Total Funding: $17,155,000
Funding Source: Mayoral

Location

Calvert Vaux Park, Brooklyn
Shore Parkway between Bay 44th & Bay 49th Streets.
Community Board: 13

 

Project Staff

Project Liaison: Davey Ives