Coney Island Boardwalk Reconstruction, Brighton 15th Street to Coney Island Avenue
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the Coney Island Boardwalk between Brighton 15th Street and Coney Island Avenue and the entrance at Brighton 15th Street.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2009
Projected Completion Date:
June 2013
Completion Date:
December 2013
Procurement
Start Date: December 2013
Projected Completion Date:
September 2014
Completion
Date:
August 2014
Construction
Start Date: November 2014
Projected Completion Date:
May 2016
Completion Date: May 2016
Understand how we build parks.
Funding
Funding Source: State
Location
Coney Island Beach & Boardwalk, Brooklyn
Brighton 15th Street and Coney Island Avenue
Community Board: 13, 15
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Documents
Last updated: 11/22/2024