Coney Island Boardwalk Reconstruction, Brighton 15th Street to Coney Island Avenue

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the Coney Island Boardwalk between Brighton 15th Street and Coney Island Avenue and the entrance at Brighton 15th Street.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2009
Projected Completion Date: June 2013
Completion Date: December 2013

Procurement

Start Date: December 2013
Projected Completion Date: September 2014
Completion Date: August 2014

Construction

Start Date: November 2014
Projected Completion Date: May 2016
Completion Date: May 2016

Understand how we build parks.

Funding

Total Funding: $6,974,000
Funding Source: State