Coney Island Beach and Boardwalk Entrance Gardens Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct new, attractive entrances to the beach and boardwalk at Brighton 2nd Street and West 33rd Street featuring new accessible ramps, stairs, seating areas, paths, benches, fences, lighting, railing and plantings.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2011
Completion Date:
January 2012
Procurement
Start Date: January 2012
Projected Completion Date:
October 2012
Completion
Date:
August 2012
Construction
Start Date: October 2012
Projected Completion Date:
October 2013
Completion Date: April 2015
Understand how we build parks.
Funding
Funding Source: State
Location
Coney Island Beach & Boardwalk, Brooklyn
Coney Island Boardwalk at Brighton 2nd Street and at West 33rd Street
Community Board: 13, 15
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024