Brooklyn General Site Work (BG-1007M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct play equipment, safety surfacing, skate parks, pavements, and plantings at various parks in Brooklyn.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2008
Projected Completion Date: March 2010
Completion Date: February 2011

Procurement

Start Date: February 2011
Projected Completion Date: November 2011
Completion Date: November 2011

Construction

Start Date: March 2012
Projected Completion Date: September 2013
Completion Date: October 2013