Brooklyn General Site Work (BG-711M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct tennis courts and basketball courts at various parks in Brooklyn.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2011
Completion Date: September 2011

Procurement

Start Date: September 2011
Projected Completion Date: June 2012
Completion Date: November 2012

Construction

Start Date: December 2012
Projected Completion Date: June 2014
Completion Date: June 2014

Understand how we build parks.

Funding

Total Funding: $2,737,000
Funding Sources:
  • City Council
  • Private

Locations

  • Bensonhurst Park, Brooklyn
    Cropsey Avenue between 21 Avenue and Bay Parkway
    Community Board: 11
  • Dean Playground, Brooklyn
    Dean To Bergen Sts Bet 6 and Carlton Avs
    Community Board: 08
  • Hamilton Metz Field, Brooklyn
    Albany, E New York, Lefferts Avs
    Community Board: 09
  • Manhattan Beach Park, Brooklyn
    Oriental Blvd. bet. Ocean Ave. and Mackenzie St.
    Community Board: 15
  • McCarren Park, Brooklyn
    N. 12 St., Lorimer St., Manhattan Ave. bet. Bayard St. and Berry St. - Nassau Ave.
    Community Board: 01
  • South Oxford Park, Brooklyn
    S. Oxford St. bet. Commos and Atlantic Ave.
    Community Board: 02
  • Multisite in Brooklyn
 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024