Banneker Playground and Tilden Playground Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the Public Restroom Buildings at Banneker Playground and Tilden Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2018
Projected Completion Date:
January 2019
Completion Date:
February 2019
Procurement
Start Date: February 2019
Projected Completion Date:
November 2019
Completion
Date:
March 2021
Construction
Start Date: April 2021
Projected Completion Date:
April 2023
Completion Date: January 2023
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Locations
-
Banneker Playground, Brooklyn
Marcy Avenue, Kosciuszko Street
Community Board: 03 -
Tilden Playground, Brooklyn
Tilden Av, E 48 To E 49 Sts
Community Board: 17
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 01/17/2025