Banneker Playground and Tilden Playground Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the Public Restroom Buildings at Banneker Playground and Tilden Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2018
Projected Completion Date: January 2019
Completion Date: February 2019

Procurement

Start Date: February 2019
Projected Completion Date: November 2019
Completion Date: March 2021

Construction

Start Date: April 2021
Projected Completion Date: April 2023
Completion Date: January 2023

Understand how we build parks.

Funding

Total Funding: $1,689,000
Funding Sources:
  • City Council
  • Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024