Pulaski and Tilden Playground Tennis Court and Play Area Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the multi-purpose play area at Pulaski Playground and the tennis courts located at Tilden Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2010
Completion Date:
July 2011
Procurement
Start Date: July 2011
Projected Completion Date:
April 2012
Completion
Date:
September 2012
Construction
Start Date: March 2013
Projected Completion Date:
March 2014
Completion Date: October 2013
Understand how we build parks.
Funding
Funding Source: City Council
Locations
-
Pulaski Playground, Brooklyn
Hart Street between Throop and Marcus Garvey Boulevard
Community Board: 03 -
Tilden Playground, Brooklyn
Tilden Avenue, East 48 to East 49 Streets
Community Board: 17
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025