Prospect Park Litchfield Villa Boiler and HVAC Systems Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the boiler and HVAC systems at the Litchfield Villa Annex in Prospect Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2011
Completion Date:
June 2012
Procurement
Start Date: June 2012
Projected Completion Date:
March 2013
Completion
Date:
January 2014
Construction
Start Date: October 2014
Projected Completion Date:
October 2015
Completion Date: December 2015