Lott House Landscape Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a vegetable garden, orchard, hedgerow, windbreak, ornamental plantings, a portion of the farm drive, custom seating, a drinking fountain, an outhouse and a wellhouse at the Lott House.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2008
Completion Date: July 2011

Procurement

Start Date: July 2011
Projected Completion Date: April 2012
Completion Date: October 2012

Construction

Start Date: May 2013
Projected Completion Date: April 2014
Completion Date: May 2015

Understand how we build parks.

Funding

Total Funding: $1,052,000
Funding Source: City Council

Location

Hendrick I. Lott House, Brooklyn
1940 East 36th Street
Community Board: 18

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024