Wyckoff House Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the roof at the Wyckoff House in M. Fidler/Wyckoff House Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2011
Projected Completion Date: April 2015
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: May 2017

Construction

Start Date: July 2017
Projected Completion Date: July 2018
Completion Date: June 2018

Understand how we build parks.

Funding

Total Funding: $385,000
Funding Source: State

Location

Fidler-Wyckoff House Park, Brooklyn
Ditmas Avenue and Clarendon Road
Community Board: 17

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024