Brownsville Recreation Center Pool HVAC System Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the pool HVAC system at Brownsville Recreation Center.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2010
Projected Completion Date: January 2011
Completion Date: January 2012

Procurement

Start Date: January 2012
Projected Completion Date: October 2012
Completion Date: September 2012

Construction

Start Date: October 2012
Projected Completion Date: September 2013
Completion Date: March 2014

Understand how we build parks.

Funding

Total Funding: $1,550,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Brownsville Playground, Brooklyn
1555 Linden Boulevard
Community Board: 16

 