Brownsville Recreation Center Pool HVAC System Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the pool HVAC system at Brownsville Recreation Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2010
Projected Completion Date:
January 2011
Completion Date:
January 2012
Procurement
Start Date: January 2012
Projected Completion Date:
October 2012
Completion
Date:
September 2012
Construction
Start Date: October 2012
Projected Completion Date:
September 2013
Completion Date: March 2014
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Brownsville Playground, Brooklyn
1555 Linden Boulevard
Community Board: 16
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024