This project will construct an Imagination Playground that will include a water, sand and block play area in Betsy Head Playground Reconstruction.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2011
Projected Completion Date:
March 2013
Completion Date:
September 2013
Procurement
Start Date: September 2013
Projected Completion Date:
June 2014
Completion
Date:
June 2014
Construction
Start Date: September 2014
Projected Completion Date:
December 2015
Completion Date: December 2015
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Betsy Head Park, Brooklyn
Dumont Avenue between Hopkinson Avenue and Bristol Street
Community Board: 16
Project Staff
Project Liaison: Davey Ives