Betsy Head Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct an Imagination Playground that will include a water, sand and block play area in Betsy Head Playground Reconstruction.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2011
Projected Completion Date: March 2013
Completion Date: September 2013

Procurement

Start Date: September 2013
Projected Completion Date: June 2014
Completion Date: June 2014

Construction

Start Date: September 2014
Projected Completion Date: December 2015
Completion Date: December 2015

Understand how we build parks.

Funding

Total Funding: $4,828,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Betsy Head Park, Brooklyn
Dumont Avenue between Hopkinson Avenue and Bristol Street
Community Board: 16

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project