Fort Washington Park Retaining Wall Reconstruction
-
80% complete
-
5% complete
-
0% complete
This project will reconstruct a retaining wall along Riverside Drive Service Road at West 161st Street in Fort Washington Park.
Project Notes
Project Update: Parks staff members are reviewing construction documents for this project.
NYC Parks staff members are currently reviewing the scope of the work order.
Project Timeline
Design
Assigned & Start Date: July 2024
Projected Completion Date:
September 2025
Procurement
Start Date: March 2025
Projected Completion Date:
August 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Fort Washington Park, Manhattan
Project Staff
Project Liaison: Contact Us
Contact NYC Parks
about this project
Last updated: 03/28/2025