Fort Washington Park Retaining Wall Reconstruction

  • Design
    80% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct a retaining wall along Riverside Drive Service Road at West 161st Street in Fort Washington Park.

Project Notes

Project Update: Parks staff members are reviewing construction documents for this project.

NYC Parks staff members are currently reviewing the scope of the work order.

Project Timeline

Design

Assigned & Start Date: July 2024
Projected Completion Date: September 2025

Procurement

Start Date: March 2025
Projected Completion Date: August 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Fort Washington Park, Manhattan

 

Project Staff

Project Liaison: Contact Us
Contact NYC Parks about this project

Last updated: 03/28/2025