Bill Brown Playground Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the Public Restroom Building in Bill Brown Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2011
Projected Completion Date: December 2012
Completion Date: October 2013

Procurement

Start Date: October 2013
Projected Completion Date: June 2014
Completion Date: July 2014

Construction

Start Date: February 2015
Projected Completion Date: August 2016
Completion Date: June 2019

Understand how we build parks.

Funding

Total Funding: $4,124,000
Funding Sources:
  • City Council
  • Mayoral

Location

Bill Brown Playground, Brooklyn
Bedford Avenue, Avenue X, Avenue Y, East 24th Street
Community Board: 15

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project