Sara D. Roosevelt Park BRC Senior Center Windows and HVAC Reconstruction (Supplemental WO 2B)

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the windows and HVAC systems at the BRC Senior Center in Sara D. Roosevelt Park.

Project Notes

Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.

Project Timeline

Design

Assigned & Start Date: August 2024
Projected Completion Date: January 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Sara D. Roosevelt Park, Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024