Alfred E. Smith Recreation Center Fitness Room Reconstruction

  • Design
    30% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the fitness room in Alfred E. Smith Recreation Center.

Project Notes

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

NYC Parks staff members are currently reviewing the scope of the work order.

Project Timeline

Design

Assigned & Start Date: August 2024
Projected Completion Date: January 2025

Procurement

Start Date: August 2024
Projected Completion Date: January 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Alfred E. Smith Playground, Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024