Alley Pond Park Path Reconstruction
-
30% complete
-
5% complete
-
0% complete
This project will reconstruct the paths surrounding the parking lot at 76th Avenue and Springfield Boulevard at Alley Pond Park.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
NYC Parks staff members are currently reviewing the scope of the work order.
Project Timeline
Design
Assigned & Start Date: October 2024
Projected Completion Date:
January 2025
Procurement
Start Date: November 2024
Projected Completion Date:
April 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Alley Pond Park, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024