John Paul Jones Park Pavement Reconstruction
-
30% complete
-
5% complete
-
0% complete
This project will reconstruct pavement in John Paul Jones Park.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
NYC Parks staff members are currently reviewing the scope of the work order.
Project Timeline
Design
Assigned & Start Date: September 2024
Projected Completion Date:
November 2024
Procurement
Start Date: October 2024
Projected Completion Date:
March 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
John Paul Jones Park, Brooklyn
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024