Abe Stark Skating Rink Boiler and Chiller Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This contract will reconstruct the boiler and chiller at the Abe Stark skating rink.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2010
Completion Date: November 2011

Procurement

Start Date: November 2011
Projected Completion Date: July 2012
Completion Date: November 2012

Construction

Start Date: December 2012
Projected Completion Date: December 2013
Completion Date: August 2014

Understand how we build parks.

Funding

Total Funding: $3,764,000
Funding Sources:
  • City Council
  • Federal
  • Mayoral

Location

Coney Island Beach & Boardwalk, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024