Taqwa Community Farm Water Service Installation
-
100% complete
-
100% complete
-
100% complete
This project will install water service at Taqwa Community Farm.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2024
Projected Completion Date:
August 2024
Completion Date:
August 2024
Procurement
Start Date: June 2024
Projected Completion Date:
November 2024
Completion
Date:
August 2024
Construction
Start Date: September 2024
Projected Completion Date:
December 2024
Completion Date: October 2024
Understand how we build parks.
Funding
Funding Source: Borough President
Last updated: 11/22/2024