Taqwa Community Farm Water Service Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install water service at Taqwa Community Farm.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2024
Projected Completion Date: August 2024
Completion Date: August 2024

Procurement

Start Date: June 2024
Projected Completion Date: November 2024
Completion Date: August 2024

Construction

Start Date: September 2024
Projected Completion Date: December 2024
Completion Date: October 2024

Understand how we build parks.

Funding

Total Funding: $300,000
Funding Source: Borough President