Mafera Park Synthetic Turf Field Reconstruction
-
90% complete
-
100% complete
-
0% complete
This project will reconstruct the synthetic turf field at Mafera Park.
Project Notes
Project Update: All contract documents are now in final review to complete the design process.
Project Timeline
Design
Assigned & Start Date: April 2024
Projected Completion Date:
December 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Mafera Park, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024