Riverside Park 107th-108th Streets Synthetic Turf Field Reconstruction

  • Design
    30% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct the synthetic turf field at West 107th-108th Streets in Riverside Park.

Project Notes

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

The budget approval documents are currently under review by the NYC Office of Management and Budget.

Project Timeline

Design

Assigned & Start Date: April 2024
Projected Completion Date: December 2024

Procurement

Start Date: June 2024
Projected Completion Date: November 2024

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Riverside Park, Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024