Riverside Park 107th-108th Streets Synthetic Turf Field Reconstruction

  • Design
    90% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the synthetic turf field at West 107th-108th Streets in Riverside Park.

Project Notes

Project Update: All contract documents are now in final review to complete the design process.

Project Timeline

Design

Assigned & Start Date: April 2024
Projected Completion Date: December 2024

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: $1,343,000
Funding Source: Mayoral

Location

Riverside Park, Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024