Calvert Vaux Park Aquatic and Coastal Upland Habitat Restoration
-
100% complete
-
100% complete
-
100% complete
This project will construct a 3.5-acre natural habitat for waterfowl by excavating existing fill material, re-grading steep slopes and creating inter-tidal zones. It will also include a new boat launch ramp, fencing, and plantings.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2001
Projected Completion Date:
October 2002
Completion Date:
January 2009
Procurement
Start Date: January 2009
Projected Completion Date:
October 2009
Completion
Date:
July 2011
Construction
Start Date: September 2011
Projected Completion Date:
August 2012
Completion Date: August 2013
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
- State
Location
Calvert Vaux Park, Brooklyn
Shore Parkway near Bay 49th Street
Community Board: 13
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025