Harris Park Turf Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the turf field at Harris Park

Project Notes

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Assigned & Start Date: April 2024
Projected Completion Date: December 2024
Completion Date: November 2024

Procurement

Start Date: June 2024
Projected Completion Date: November 2024
Completion Date: November 2024

Construction

Start Date: October 2024
Projected Completion Date: April 2025