Alfred E. Smith Park Recreation Center Gymnasium Lights Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the gymnasium lights in the Alfred E. Smith Park Recreation Center

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2024
Projected Completion Date: July 2024
Completion Date: April 2024

Procurement

Start Date: March 2024
Projected Completion Date: August 2024
Completion Date: May 2024

Construction

Start Date: June 2024
Projected Completion Date: September 2024

Understand how we build parks.

Funding

Total Funding: $29,000
Funding Source: Mayoral

Location

Alfred E. Smith Playground, Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024